Process and Closure of Non-Conformance Operation

This document provide the information how to complete the Non Conformance operations 

To complete the Non Conformance operations please follow the steps given below

  • To Schedule the Non Conformance operation record, Navigate to -> Menu Category.
  • Select Quality menu category.
  • Navigate to -> Quality -> Non conformance.
  • Click on -> Approved Non Conformance record.
  • Navigate to -> Operations tab.
  • Click on -> Operation record -> Scheduled button.
  • Non-conformance operation status marked as Scheduled.
  • Similarly, mark all the operations as Scheduled.
  • After schedule the operations failed quality check items moved to Non conformance location.

 

Schedule button on Non Conformance Operation

 

  • Click on -> In-Progress button.
  • Non-conformance operation status marked as In-Progress.
  • Similarly, mark all the operations as In-Progress.

 

 In-Progress button on Non Conformance Operation

 

  • Click on -> Complete button.
  • Non-conformance operation status marked as Completed.
  • Similarly, mark all the operations as Completed.
  • When non-conformance operation change operation status as completed, then non conformance status marked as Fixed.

 

Completed Non Conformance Operation

 

Fixed Non conformance